24 Nisan, 2009

MATERIAL REQUIREMENTS PLANNING

MRP SYSTEM


 

Material requierements management is a computerized inventory control and production planning system. It has the most stringent and complete control over the entire process. It starts with the demand for a product and then, using the bill of materials that show how the product is made, multiplies items for item down through the entire chain. This gives the number of each item needed to produce that number of product. Further, it not only tabuletes the number of items, but it also considers the time it takes to make each item in the cain. The final result is a schedule that shows the number of each item needed in the sequence and the time in which it must be produced.


 


 


 

PURPOSES,OBJECTIVES AND PHILOSOPHY OF MRP


 

The main
purposes

of a basic MRP system are;


 

  • To control inventory levels,
    • Order the right part.
    • Order in the right quantitiy.
    • Order at the right time.
  • To assign operating priorities for items,
    • Oreder with the right due date.
    • Keep the due date valid.
    • To plan capacityto load the production system,
      • Plan for a complete load.
      • Plan an accurate load.
      • Plan for an adequate time to view future load.

    

    The theme
of MRP is "getting the right materials to the right place at the right time."

    
 

The objectives
of inventory management under an MRP system are;


 

  • To improve customer service.
  • To reduce inventory investment.
  • To improve plant operating efficiency.


 

The philosophy of MRP is that materials should be expedited when their lack would delay the overall production schedule falls behind and postpones their need.


 


 

BENEFITS OF MRP SYSTEM


 

Some of the most important benefits of MPR system are;


 

  • Increases sales.
  • Reduces sales price.
  • Reduces inventory.
  • Better customer service.
  • Better response to market demands.
  • Ability to change the master schedule.
  • Reduces setup and tear-down costs.
  • Reduces idle time.
  • Gives advance notice.
  • Tells when to de-expedite as well as expedite.
  • Delays or cancels oreders.
  • Changes order quantities.
  • Advances or delays order due dates.
  • Aids capacity planning.


 


 


 

MATERIAL REQUIREMENTS PLANNING STRUCTURE


 

MRP system works as follows;


 

  1. Orders for products are used to create a master production schedule,which states the number of items to be produced during spesific time period.
  2. A bill of materials file identifies the specific materials that are used to make each item and the correct quantities of each.
  3. The invetory records file contains data such as the number of units on hand and on order.


 


 

These 3 sources become the data sources for the Materials Requirements program, which expands the production schedule into detailed order scheduling plan for the entire production sequence.We will now discuss these element in detail.


 


 


 


 


 


 


 


 

EXHIBIT 1 Material Requirements Planning System Structure


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 

  • MRP Inputs


 

  1. Master Production Schedule;


 

The master production schedule (MPS) specifies

  • which items or finished products a firm is to produce,
  • how many are needed,
  • when they are needed.

The master production schedule works within the constraints of the production plan but produces a more specific scedule by individual products.The time frame is more specific, too. An MPS is usually expressed in days or weeks and may extend over several months to cover the complete manufacture of the items contained in the MPS.The total length of time required to manufacture a product is called its cumulative lead time.

Exhibit 2 shows a sample MPS consisting of 4 end items.


 


 

EXHIBIT 2-Master Production Schedule (MPS)


 


P E R I O D SMPS Item12345678Item A78931408080808080Item B060060060060Item C501105720171000Item D100100100100100100100100

Several comments should be made concerning the quantities contained inthe MPS;
the quantities represent production, not demand
 

  • The quantities may consist of a combination of customer orders and demand forecasts
  • The quantities represent what needs to be produced, not what can be produced.


 


 


 

  1. Product Structure File


 

Once the MPS set, the MRP system accesses the product structure file to determine which component items need to be scheduled. The product structure file contains a bill of material (BOM) for every item produced. The bill of material for a product lists the items that go into the product, includes a brief description of each item, and specifies when and in what quantity each item is needed in the assembly process.


 

When each item is needed can be best described in the form of a product structure diagram, as shown in Exhibit3 for a wheelbarrow.An assembled item sometimes called a "parent" and a component is called "child".The number in paranthesis beside each item is the quantitiy of the component to make one parent.


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 

EXHIBIT 3-Product Structure Tree Showing BOM Levels.


 


 


 


 

A diagram can be converted to a computerized bill of material by labeling the levels in the product structure. Exhibit 4 shows some levels intended underneath others. This specifies which component belong to which parent.


 


 

EXHIBIT 4 – Intended Bill of Material


 


 

Level 

Item 

Quantitiy 

units 

0------ 

wheelbarrow 

1 

each 

--1------ 

box 

1 

each 

--1------ 

handle assembly 

1 

each 

----2---- 

bars 

2 

each 

----2---- 

grips 

2 

each 

--1------ 

wheel assembly 

1 

each 

----2----

axle 

1 

each 

----2---- 

bearings 

2 

each 

----2---- 

wheel 

1 

each 

------3-- 

tire 

1 

each 

--1------ 

paint 

1 

each 


 


 


 


 


 


 


 


 

  1. Inventory Master File:


     

The inventory master file contains an extensive amount of information on every item that is produced, ordered or, inventoried in the system. It includes such data as on-hand quantities, on order quantities, lot sizes, safety stock, lead time, and past usage figures. It provides a detailed description of the item, specifies the inventory policy,updates the phyisical inventory count, summarizes thr item's year-to-date or month-to-date usage, and provides internal codes to link this file with other related ,nformation in the MRP database. Exhibit
5 displays the inventory master file of a "board" assembly from a clipboard assembly.


 


 

EXHIBIT 5- Inventory Master File


 


 

Description 

Inventory Policy

 

ITEM 

Board 

LEAD TIME 

2 

ITEM NO 

7341 

ANNUAL DEMAND  

5000 

ITEM TYPE 

manufacturing 

HOLDING COST 

1 

PRODUCT/SALES CLASS 

Ass'y 

ORDERING/SETUP COST 

50 

VALUE CLASS 

B 

SAFETY STOCK

25 

BUYER/PLANNER 

RSR 

REORER POINT 

39 

VENDOR/DRWAING 

7142 

EOQ 

316 

UNIT PRICE/COST 

1,25 

MIN ORDER QTY. 

100 

PEGGING 

Y 

MAX ORDER QTY. 

500 

LLC 

1 

MULTIPLE ORDER QTY 

100 

  

POLICY CODE 

3 

Physical Inventory 

Usage /sales 

ON HAND 

100 

YTD usage /sales 

1100

LOCATION 

W142 

MTD usage /sales 

75 

ON ORDER 

100 

YTD usage /sales 

1200 

ALLOCATED 

75 

MTD receipts 

0 

CYCLE 

3 

Last receipt 

8/25 

LAST COUNT 

09.May 

Last issue 

10/5 

DIFFERENCE 

-2 

  


 


 


 


 


 


 


 


 

Codes 

Cost Acct. 

00754 

Routing 

00326 

Engineering 

07142 


 


 


 


 


 


 


 


 


 


 


 


 

  • MRP Process


 

The MRP system is responsible for scheduling the production of all items beneaththe end item level. It reccomends the release of work orders and purchase oerders, and issues rescheduling notices when necessary.the MRP process includes;

  • Explosion
  • Netting
  • Lead time offsetting.


     

    We will explain the MRP proceess in the example part. Now,we only describe the worksheet called the MRP matrix
    to record the calculations that are made and make a brief description of the entries taht are required.


     

    EXHIBIT 6 -The MRP Matrix


     


     


     

    Item: LLC: 

    PERIOD 

    Lot Size: LT: 

    PD 

    1 

    2 

    3 

    4 

    5 

    6 

    7 

    8 

    9 

    10 

    Gross Requirements 

               

    Scheduled Receipts 

               

    Projected on Hand 

               

    Net requirements 

               

    Planned Order Receipts 

               

    Planned Order Releases 

               


     


     

    • Item:the name or the number of the item being scheduled
    • LLC:low level code;the lowest level that the item appears in a product structure
    • Lot size:normally an order will be placed in multiples of this quantity;but it can also represent a minimmum or maximmum order quantity or the type of lot sizing technique.
    • PD:past-due time bucket. If an order appears in the PD time bucket, the schedule is infeasible and an error message will be generated. Projected on hand entries in the PD column represent beginning inventory.
    • Gross Requirements: the demand for an item by time period.

    For an end item this quantity is obtained from MPS.

    For a lower- level item, it is derived from the planned order releases of its parents


     

    • Scheduled receipts: the quantity of material that is already ordered and when it is expected to arrive.
    • Projected on hand:
      the expected quantitiy
      in inventory at the end of a period that will be available for demand in subsequent perods.
    • Net requirements:
      the net number of items that must be provded and when they are needed.
    • Planned order receipts: net requirements adjusted for lot sizing
    • Planned order releases: planned order receipts offset for lead times. It shows when an order should be placed so that items are available when needed.


     


     

    • MRP Outputs

    The outputs of MRP process are planned orders from the planned order release row of the MRP matrix. These can represent;

    • Work orders to be released to the shop floor for in house production
    • Purchase orders to be sent to outside suppliers
    • Rescheduling notices or action notices which are issued for items that are no longer needed as soon as planned or for quantities that may have changed.


     

    EXHIBIT 7- Planned Order Report


     

    Item #2740 Date: 9/26/02

    On Hand 100 Lead time 2 weeks

    On order 200 Lot size 200

    Allocated 50 Safety stock 50 


     

    Date 


     

    Order no. 

    Gross requirements

    Scheduled

    receipts 

    Projected on hand(50) 


     

    Action 

        

    50 

     

    9/26 

    AL 4416  

    25 

     

    25 

     

    9/30 

    AL 4174 

    25 

     

    0 

     

    10/01 

    GR6470 

    50 

     

    -50 

     

    10/08 

    SR 7452 

     

    200 

    150 

    Exepedite SR10-01 

    10/10 

    CO 4471 

    75 

     

    75 

     

    10/15 

    GR 6471 

    50 

     

    25 

     

    10/23 

    GR 6471 

    25 

     

    0 

     

    10/27

    GR6473 

    50 

     

    -50 

    Release PO 10-13 


     


     

    EXHIBIT 7- MRP Action Report


     


     

    Current Date:9/25/02 

    Item 

    Date 

    Order no 

    Qty. 

    Action 

    #2740 

    10/08 

    7542 

    200 

    expedite SR 10/01 

    #3616 

    10/09 

      

    move forward PO 10/07 

    #2412 

    10/10 

      

    move forward PO 10/05

    #3427 

    10/15 

      

    move backward PO 10/25 

    #2516 

    10/20 

    2648 

    100 

    de-expedite SR 10/30 

    #2740 

    10/27 

     

    200 

    release PO 10/13 

    #3666 

    10/31 

     

    50 

    release WO 10/24 

    To expedite an order is to speed it up so it is completed in less than its normal lead time.

    The process of moving some jobs bacj-kward(de-expediting) and moving other jobs forward in the schedule (expediting) allows material planner, with the aid of the MRP system, to fine tune the plan.


     

    AN EXAMPLE USING MRP


     

        Ampere Inc., produces a line of electric meters installed in residential buildings by electric utility companies to measure power consumption. Meters used on single-family homes are of two basic types for different voltage and amperage ranges. In addition to complete meters, some parts and subassemblies are sold separately for repair or for changeovers to a different voltage or power load. The problem for the MRP system is to determine a production schedule that would identify each item, the period it is needed, and the appropriate quantities. This schedule is checked for feasibility, and the schedule is modified if necessary.


     

        Demand for the meters and components originate from two sources: regular customers that place firm orders, and unidentified customers that make the normal random demands for these items.

    Exhibit-8 shows the future requirements for Meters and B, Subassemblies D and Part E for a six months period stemming from specific customer orders and random sources.


     


     


     

    EXHIBIT 8


     


     


     

    Month

    3

    4

    5

    6

    7

    Meter A

    Known Random

    1000 250

    1. 250

    300 250

    700 250

    600 250

    700 250 

    Meter B

    Known Random

    400 60

    300 60

    500 60

    400 60

    300 60

    700 60 

    Subassembly D

    Known Random

    200 70

    180 70

    250 70

    200 70

    150 70

    160 70 

    Part E

    Known Random

    300 80

    350 80

    300 80

    250 80

    200 80

    200 80


     


     


     


     


     


     


     


     


     


     

    Developing a Master Production Schedule


     

        Our schedule will assume that all items are to be available the first week of t he month. This assumption is reasonable since management prefers to produce meters in one single lot each month rather than a number of lots throughout the month.

    Exhibit-9 shows the trial master schedule that we use under these conditions, with demands for months 3 and 4 shown as the first week of the month, or as weeks 9 and13. We will work only with these two demand periods.


     

    EXHIBIT 9


     

     

    Week 

    9 10 11 12 13 14 15 16 17  

    Meter A 

    1250     850     550

    Meter B 

    460 360 560 

    Subassembly D 

    270 250 320

    Part E 

    380 430 380 


     


     


     

    Bill of Materials (Product Structure) File


     

        The product structure for Meters A and B is shown in Exhibit-10 in the typical way using low-level coding, in which each item is placed at the lowest level at which it appears in the structure hierarchy. Meters A and B consist of two sub assemblies, C and D, and two parts, E and F. Quantities in parentheses indicate the number of units required per unit of the parent item.


     

    EXHIBIT 10


     


     

        Exhibit-11 shows an indented parts list for the structure of Meters A and B. The BOM file carries all items without indentation for computational ease, but indented print out clearly show the manner of product assembly.


     


     


     


     

    EXHIBIT 11


     

    Meter A    Meter B


     

    A         B

    D(1)                  E(1)

         E(1)                 F(2)

         F(1)                 C(1)

    E(2)                    D(1)

    C(1)                        E(1)

         D(1                        F(1))

             E(1)                F(2)

             F(1)

         F(2)    


     

    Inventory Records Item (Item Master) File


     


     

        The inventory records file contains much additional data, such as vendor identity, cost and lead times. For this example, the pertinent data contained in the inventory records file are the on-hand inventory at the start of the program run and the lead times. These data are taken from the inventory records file and shown in Exibit-12.


     


     


     

    EXHIBIT 12


     

            On-hand         Lead Time

    Item        Inventory        (weeks)

    A    50    2

    B    60    2

    C    40    1

    D    30    1

    E    30    1

    F    40    1


     


     


     


     


     


     


     


     


     


     


     

    Running the MRP Program


     

        The correct conditions are now set to run the MRP computer program – end item requirements have been established through the master production schedule, the status of inventory and the order lead times are contained in the inventory item master file, and the bill of materials file contains the product structure data. The MRP program now explodes the item requirements according to the BOM file, level by level, in conjunction with the inventory records file. A release date for the net requirements order is offset to an earlier time period to account for the lead time. Orders for parts and subassemblies are added through the inventory file, by passing the master production schedule, which, ordinarily, does not schedule at a low enough level to include spares and repair parts.

        Exhibit-13 shows the planned order release date for this particular run. The program logic can best be understood by following the analysis below. (We will confine our analysis to the problem of meeting the gross requirements for 1250 units of Meter A, 460 units of Meter B, 270 units of Subassembly D and 380 units of Part E, all in week 9.)

        The 50 units of A on hand result in a net requirement of 1200 units of A. To receive Meter A in week 9, the order must be placed in week 7 to account for the two-week lead time. The same procedure follows for Item B, resulting in a planned 400-unit order released in period 7.

        The rational for these steps is that for an item to be released for processing, all its components must be available. The planned order release date for the parent item therefore becomes the same gross requirement period for the subitems.

         Referring to Exhibit-3, level 1, one unit of C is required for each A and each B. Therefore, the gross requirements for C in week 7 are 1600 unit (1200 for A and 400 for B) . Taking into account the 40 units on hand and the one-week led time, 1560 units of C must be ordered in week 6.

        Level 2 of Exhibit-3 shows that one unit of D is required for each A and each C. The 1200 units of D required for A are gross requirements in week 7, and the 1560 units of D for item C are the gross requirements for week 6. Using the on-hand inventory first and the one-week lead time result in the planned order releases for 1530 units in week 5 and 1200 units in week 6.


     


     


     


     


     


     


     


     


     


     


     


     


     


     


     


     

    EXHIBIT 13


     


     

    Item 

    Week 

    10 

    11 

    12 

    13 


     

    A (LT=2)

    Gross requirements

    On hand 50

    Net requirement

    Planned-order receipt

    Planned-order release


     

       


     


     


     


     


     


    1200

     


     


     

    1250

    50

    1200

    1200

       


     


     

    850


     

    B (LT=2)

    Gross requirements

    On hand 60

    Net requirement

    Planned-order receipt

    Planned-order release

       


     


     


     


     


     


    400

     


     


     

    460

    60

    400

    400

       


     


     

    360 


     

    C (LT=1)

    Gross requirements

    On hand 40

    Net requirement

    Planned-order receipt

    Planned-order release

      


     


     


     


     


     

    1560


     

    400

    1200

    40

    1560

    1560

          


     

    D (LT=1)

    Gross requirements

    On hand 30

    Net requirement

    Planned-order receipt

    Planned-order release

     


     


     


     


     


     


     


     

    1530


     

    1560

    30

    1530

    1530

    1200


     


     

    1200

    0

    1200

    1200

     


     


     


     


     


     


    270


     


     

    270

    0

    270

    270

       


     


     

    250 


     

    E (LT=1)

    Gross requirements

    On hand 30

    Net requirement

    Planned-order receipt

    Planned-order release


     


     


     


     


     


     


     


    1500


     


     

    1530

    30

    1500

    1500

    1200


     


     

    1200

    0

    1200

    1200

    2800


     

    2400

    400

    0

    2800

    2800


    270


     


     

    270

    0

    270

    270

    380


     


     

    380

    0

    380

    380

       


     


     

    430


     

    F (LT=1)

    Gross requirements

    On hand 40

    Net requirement

    Planned-order receipt

    Planned-order release


     


     


     


     


     

    1490


     


     

    1530

    40

    1490

    1490

    4320


     

    3120

    1200

    0

    4320

    4320

    800


     


     

    800

    0

    800

    800

    270


     


     

    270

    0

    270

    270

         


     


     


     


     


     


     


     


     


     


     


     


     

    Level-3 contains Items A and F. because E and F are each used in several places, Exhibit-7 is presented to identify more clearly the parent item, the number of units required for each parent item, and the week in which it is required. Two units of Item E are used in each Item A. the 1200-unit planned order released for A in period 7 becomes to gross requirement for 2400 units of E in the same period. One unit of E is used in each B, so the planned order released for 400 units of B in period 7 becomes the gross requirement for 400 units of E in week 7. Item E is also used in Item D at the rate of one per unit. The 1530-unit planned order released for D in period 5 becomes to gross requirement for 1530 units of E in period 5 and a 1530-unit planned order release in period 4 after accounting for the 30 unit on hand the one-week lead time. The 1200-unit planned order release for D in period 6 results in gross requirement for 1200 units of E in week 6 and a planned order release for 1200 units in week 5.

    Item F used in B, C, and D. The planned order releases for B, C, and D become the gross requirement for F for the same week, except that the planned order release for 400 units of B and 1560 of C become gross requirement for 800 and 3120 units of F, since the usage rate is two per unit.

    The independent order for 270 units of subassembly D in week 9 is handled as an input to D's gross requirement for that week. This is then exploded into the derived requirements for 270 units of E and F. The 380-unit requirement for part E to meet an independent repair part demand is fed directly into the gross requirement for Part E.

    The independent demands for week 13 have not been exploded as yet.

    The bottom line of each item in Exhibit-6 is taken as a proposed loan on the productive system. The final production schedule is developed manually or with the firm's computerized production package. If the schedule is infeasible or the loading unacceptable, the master production schedule is revised and the MRP package is run again with the new master schedule.


     


     

    EXHIBIT 14


     

    Item 

    Parent 

    Number of Units per Parent 

    Resultant Gross Requirement 

    Gross Requirement Week 

    C

    C

    D

    D

    E

    E

    E

    E

    F

    F

    F

    A

    B

    A

    C

    A

    B

    D

    D

    B

    C

    D

    1

    1

    1

    1

    2

    1

    1

    1

    2

    2

    1

    1200

    400

    1200

    1560

    2400

    400

    1530

    1200

    800

    3120

    1200

    1530 

    7

    7

    7

    6

    7

    7

    5

    6

    7

    6

    6


     


     


     


     

    WHERE MRP CAN BE USED?


     

    MRP is being used in a variety of industries, all with a job-shop environment (meaning that a number of products are made in batches using the same productive equipment).The list in Exhibit 15 includes process industries, but note that the processes mentioned are confined to job runs that alternate output product and don't include continuous processes such as petroleum or steel.

        MRP doesn't work well in companies that have a low annual number of units produced. Especially for companies producing complex expensive products requiring advanced research and design, experience has shown that lead times tend to be too long and too certain, and the product configuration too complex for MRP to handle. Such companies need the control features that network scheduling (covered previously in Chapter 10).


     

    As you can see in the exhibit, MRP is most valuable to companies
    involved in assembly operations and least valuable to those in fabrication.


     


     

    EXHIBIT 15 Industry Applications and Expected Benefits


     

    Industry Type Examples Expected Benefits


     


     

    Assemble-to-stock Combines multiple component High

    parts into a finished product ,

    which is then stocked in inventory

    To satisfy customer demand.

    Examples: watches, tools, appliences.


     

    Fabricate-to-stock Items are manufactured by machine rather Low

    than assembled from parts.These are standart

    stock items carried in anticipation of customer

    demand.


    Examples:piston rings,electrical switches.


     

    Assemble-to-order A final assemble is made from standart options High

    which the customer chooses.

    Examples:trucks,generators,motors


     

    Fabricate-to-order Items manufactured by machine to customer Low

    order.These are generally industrial orders.


    Examples:bearings,gears,fasteners.


     

    Manufacture-to-order Items fabricated or assembled completely to High

    customer specification


    Examples:turbinegenerators,heavy machine

    tools.


     

    Process Industries,such as foundries,rubber and plastics. Medium


     

    CAPACITY REQUIREMENTS PLANNING (CRP)


     

    CRP is a computerized system that projects the load from a given material plan onto the capacity of a system and identifies underloads and overloads. It's then up to the MRP planner to level the load-smooth out the resource requirements so that capacity constraints aren't violated. This can be accomplished by shifting requirements, reducing requirements, or temporarily expanding capacity.


     

        There are three major inputs to CRP, as shown in Exhibit 16;


     

    • The planned order releases from the MRP process;


     

    • A routing file, which specifies which machines are required to complete an order from the MRP plan, in what order the operations are to be conducted, and the length of time each operation should take; and


     

    • an open orders file ,which contains information on the status of jobs that have already been released to the shop but have not yet been completed.


     

    With this information, CRP can produce a load profile for each machine or work center in the shop. The load profile compares released orders with work center capacity.


     


     

        EXHIBIT 16 Capacity Requirements Planning


     


     


     


     


     

    Capacity, usually expressed as standard machine hours or labor hours, is calculated as follows:

        

    Capacity = (no. machines or workers) * (no. shifts ) * (utilization) * (efficiency)


     


     

    Utilization refers to the percentage of available working time that a worker actually works or a machine actually runs. Scheduled maintenance, lunch breaks, and setup time are examples of activities that reduce actual working time. Efficiency refers to how well a machine or worker performs compared to a standard output level. Efficiency is also dependent on product mix.

        Load is the standard hours of work (or equivalent units of production) assigned to a production facility. After load and capacity have been determined, a load percent can be calculated as


     

    Load percent =
    load

    * 100%


    Capacity     


     

    Centers loaded above 100 percent will not be able to complete the scheduled work without some adjustment in capacity or reduction in load.


     


     


     


     


     

MANUFACTURING RESOURCES PLANNING (MRPII)


 

The MRP systems on the market today are composed of many different modules that can be purchased separately. Typically, the modules include the following:


 

  • Forecasting
  • Customer order entry
  • Production planning/master production scheduling
  • Product structure/bill-of-material processor
  • Inventory control
  • Material requirements planning
  • Capacity planning
  • Shop floor control
  • Purchasing
  • Accounting
  • Financial analysis


 


 


 


 


 


 

We can recognize some of these modules as inputs to or outputs from the basic MRP process. Others represent a broadened scope of MRP-related activities, beginning with forecasting demand and ending with a financial analysis of the firm.

Companies differ their approach to implementing MRP, but seldom will a company purchase an entire MRP system at one time. Most firms install the product structure/bill-of-material (BOM) processor first and then add the inventory module, followed by the MRP module. The BOM and inventory modules have large databases and serve as major inputs to the rest of the process.

    Purchasing is also brought online early, usually shortly after the BOM module is installed. Assemble-to-order companies tend to implement the customer entry module as soon as possible.

    It may be some time before the master schedule module or higher –level planning modules are added. How, you may wonder, does the MRP system run without a master schedule? Actually, a master production schedule is used, but it's not generated or maintained by the MRP system; it is input by hand.

    The capacity planning is important for a well-run MRP system, its absence often separates the successful MRP user from the unsuccessful user.

    Shop floor control is a difficult module to implement and is probably the most disappointing one in practice.

    As MRP evolved and more modules and features were added in the areas of capacity planning, marketing, and finance, it became clear that the name material requirements planning was no longer adequate to describe the full range of activities this system could coordinate. In keeping with the MRP acronym, the new and improved MRP became known as MRP II, for manufacturing resource planning. Figure 13.8 shows how the various MRP II functions interact. The term closed loop has been used to describe the numerous feedback loops between plans for production or available capacity and between planned and actual occurrences.

    Manufacturing resource planning is a misnomer because MRP II software is also used in services, such as education, architecture, health care, distribution, and the like. Thus, systems such as SRP (service requirement planning), DRP (distribution requirements planning), and BRP (business requirements planning), are also available.


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 


 

EXHIBIT 17 MANUFACTURING RESOURCES PLANNING (MRP II)


 


 


 


 


 


 


 


 


 


 

Hiç yorum yok:

Yorum Gönder